BRIDLE CREEK SUBDIVISION – PHASE 2

This is the second phase of a large sub-division south of Atlanta. Scope of work calls for tack coating all vertical edges of concrete curb and gutter, pave with 2 inches (compacted thickness) of 12.5 mm asphalt binder, and roll to proper compaction density. Our base crews installed 6 inches of GAB base material prior to paving, having final graded sub-base material and compacted for proper density. After builder has completed substantial construction of homes, we will return to lay the final layer of 1.5 inches 9.5 mm asphalt topping.